Activity cuts and resource rescheduling (ACRES) algorithm for resource-constrained project rescheduling - by Joseph Guy Hobeika
Abstract
Many heuristic algorithms, with various levels of solution optimality, have been developed for solving the problem of project scheduling under resource constraints. In most of these algorithms, the critical path method of scheduling is initially applied,
Description
Thesis (M.E.)--American University of Beirut. Department of Civil and Environmental Engineering, 1992.;"Advisor: Dr. Mohamed-Asem Abdul-Malak, Assistant Professor of Civil Engineering and Engineering Management -- Members of Committee: Dr. Moueen Salameh