Activity cuts and resource rescheduling (ACRES) algorithm for resource-constrained project rescheduling - by Joseph Guy Hobeika

Loading...
Thumbnail Image

Date

Journal Title

Journal ISSN

Volume Title

Publisher

Abstract

Many heuristic algorithms, with various levels of solution optimality, have been developed for solving the problem of project scheduling under resource constraints. In most of these algorithms, the critical path method of scheduling is initially applied,

Description

Thesis (M.E.)--American University of Beirut. Department of Civil and Environmental Engineering, 1992.;"Advisor: Dr. Mohamed-Asem Abdul-Malak, Assistant Professor of Civil Engineering and Engineering Management -- Members of Committee: Dr. Moueen Salameh