dc.contributor.author |
Hobeika, Joseph Guy |
dc.date.accessioned |
2012-06-13T06:41:28Z |
dc.date.available |
2012-06-13T06:41:28Z |
dc.date.issued |
1992 |
dc.identifier.uri |
http://hdl.handle.net/10938/4696 |
dc.description |
Thesis (M.E.)--American University of Beirut. Department of Civil and Environmental Engineering, 1992.;"Advisor: Dr. Mohamed-Asem Abdul-Malak, Assistant Professor of Civil Engineering and Engineering Management -- Members of Committee: Dr. Moueen Salameh |
dc.description |
Bibliography: leaf 62. |
dc.description.abstract |
Many heuristic algorithms, with various levels of solution optimality, have been developed for solving the problem of project scheduling under resource constraints. In most of these algorithms, the critical path method of scheduling is initially applied, |
dc.format.extent |
viii, 62 leaves : ill. cm. |
dc.language.iso |
eng |
dc.relation.ispartof |
Theses, Dissertations, and Projects |
dc.subject.classification |
ET:003518 AUBNO |
dc.subject.lcsh |
Algorithms. |
dc.title |
Activity cuts and resource rescheduling (ACRES) algorithm for resource-constrained project rescheduling - by Joseph Guy Hobeika |
dc.type |
Thesis |
dc.contributor.department |
American University of Beirut. Faculty of Engineering and Architecture. Department of Civil and Environmental Engineering |