dc.contributor.author |
Ramadan, Maysaa Mahmoud |
dc.date.accessioned |
2012-06-13T07:31:55Z |
dc.date.available |
2012-06-13T07:31:55Z |
dc.date.issued |
2010 |
dc.identifier.uri |
http://hdl.handle.net/10938/8411 |
dc.description |
Thesis (M.E.M.)--American University of Beirut, Engineering Management Program, 2010.;"Advisor : Dr. Issam Srour, Visiting Assistant Professor, Engineering Management--Member of Committee : Dr. Mohammed Assem Abdul-Malak, Professor ,Engineering Management |
dc.description |
Bibliography : leaves 107-111 |
dc.description.abstract |
Concurrent engineering is defined as the process of completing tasks in parallel, in order to reduce project delivery times. This overlapping of sequential activities is becoming a requirement for fast-tracking complex construction projects. --The nature |
dc.format.extent |
xiii, 111 leaves : ill. 30 cm. |
dc.language.iso |
eng |
dc.relation.ispartof |
Theses, Dissertations, and Projects |
dc.subject.classification |
ET:005342 AUBNO |
dc.subject.lcsh |
Scheduling -- Persian Gulf |
dc.subject.lcsh |
Concurrent engineering -- Persian Gulf |
dc.subject.lcsh |
Construction industry -- Persian Gulf |
dc.subject.lcsh |
Project management -- Persian Gulf |
dc.subject.lcsh |
Milestones -- Persian Gulf |
dc.title |
Fast-tracking the design phase of a construction megaproject when and how? - by Maysaa Mahmoud Ramadan |
dc.type |
Thesis |
dc.contributor.department |
American University of Beirut. Faculty of Engineering and Architecture. Engineering Management Program |